Agenda Date: 07/21/2026
Subject:
Title
Resolution 48-2026: Approving a Construction Contract with FNF Construction, Inc. for the Prince Street Link Project, City Project No. 18-14
Body
From:
James L. Becklenberg, City Manager
Prepared by:
Brent Soderlin, Director of Public Works & Utilities
Ray Hill, Interim City Engineer
Matthew Matuszewski, CIP Manager
Jim Brose, Civil Engineer III
Presentations:
N/A
PURPOSE:
Approving a Construction Contract with FNF Construction, Inc for the Prince Street Link Project, City Project No. 18-14.
LONG-TERM OUTCOME(S) SERVED:
Safe Community; High-Quality Governance
DISCUSSION:
On March 25, 2026, the City of Littleton's Public Works Department advertised an Invitation for Bids for the Prince Street Link Project, City Project No. 18-14. The City received two bids, which were opened on April 24, 2026. Staff reviewed the bids for fairness and accuracy; FNF Construction, Inc. was identified as the lowest responsive bidder. An overview of the project is provided in the following section.
The project is partially funded by $615,000 in Safer Main Streets grant funds from the Colorado Department of Transportation (CDOT); the City has entered into a concurrence to award agreement with CDOT to award FNF Construction, Inc. the construction contract for the Prince Street Link Project.
Council approval of this resolution is required for construction of the project to move forward. Construction is anticipated to begin in July 2026, with anticipated completion in October 2026.
BACKGROUND:
The safety of vulnerable roadway users such as pedestrians, cyclists, transit users, and those with disabilities, throughout the city is critical to a healthy city and transportation network. The Prince Street Link Project will provide safety and accessibility improvements along Prince Street between Lake Avenue to Alamo Avenue. The enhancements of the Prince Street Link Project will improve access and connections to several key destinations i...
Click here for full text